Acceptance of a completely constructed object is carried out by the customer when it is fully prepared in accordance with the approved urban planning documentation and the executive documentation, declaration of conformity, and conclusions on the compliance of the work performed with the approved urban planning documentation and on the quality of construction and installation works are available.

Acceptance of a completely constructed object related to state secrets or other secrets protected by law, as well as objects of state importance, is carried out by the state acceptance commission created by the Cabinet of Ministers of the Republic of Uzbekistan (hereinafter — the commission). At that, representatives of the customer, developer and contractor must necessarily take part in the work of the commission.

Acceptance of a completely constructed object is formalized by the certificate of final completion of the completely constructed object, which is signed by the contractor and the customer. In cases of creation of a commission, the certificate of final completion of the completely constructed object is signed by the members of the commission, the customer, the developer, the contractor and persons exercising technical and architectural supervision.

The form of the certificate of final completion of the completely constructed object is approved by a specially authorized state body.

The duties of the participants in the acceptance of the completely constructed object include:

establishment and documentary confirmation of the readiness of the completely constructed object;

assessment of the compliance of the completed construction and installation works with the approved urban planning documentation, the requirements of urban planning norms and rules;

testing of technological, engineering or other equipment (engineering systems);

establishment of compliance of the commissioned efficiency (capacity, throughput) of the object with the indicators approved in urban planning documentation.

In the event of violations of the approved design solutions and urban planning norms and rules, as well as in the case of negative conclusion of persons exercising technical and architectural supervision, the customer (commission) accepts the object into operation after the contractor has eliminated the violations.

The commissioning of a completely constructed object is carried out by issuance of a permit for the operation of the completely constructed object by the territorial inspectorate.

The grounds for issuing a permit for the operation of a completely constructed object are:

certificate of final completion of the completely constructed object;

set of post-completion documentation for the object;

declaration of conformity issued by the contractor;

a conclusion on the compliance of the work performed with the approved urban planning documentation issued by the person exercising architectural supervision;

conclusion on the quality of construction and installation works issued by the person exercising technical supervision.

The date of issue by the territorial inspectorate of a permit for the operation of the completely constructed object is considered the date of the commissioning of the object.

Operation of the constructed object without an approved certificate of final completion of the completely constructed object and permission of the territorial inspectorate for the operation of the completely constructed object is not allowed.

Providing the customer with a declaration of conformity, conclusions on the quality of construction and installation works and the compliance of the work performed with the approved urban planning documentation does not relieve the developer, contractor, persons exercising technical and architectural supervision, from responsibility for the work performed during the design, construction, acceptance and commissioning of the object.

The customer is responsible for the timely acceptance of the completely constructed object and its commissioning.

The procedure and time frame for the acceptance of the completely constructed object and its commissioning are established by the Cabinet of Ministers of the Republic of Uzbekistan.